Skip to content
Eastledge Interiors
Co-op Funeralcare, Mitcham: partitions, dry lining and suspended ceilings, Morden Road, Mitcham, south London. Interior fit-out by Eastledge.

Case study

Co-op Funeralcare, Mitcham: partitions, dry lining and suspended ceilings

Client
Co-op Funeralcare
Location
Morden Road, Mitcham, south London
Duration
August to November 2026

Eastledge delivered the partitions, dry lining, taping and jointing, suspended ceilings and fire curtains for a Co-op Funeralcare fit-out on Morden Road, Mitcham, south London. The main contractor was Kingfisher Construction and the architect was Bowman Riley. Our team started on site in August 2026 and completed the package in November 2026.

Client

Co-op Funeralcare

Location

Morden Road, Mitcham, south London

Duration

August to November 2026

Main contractor

Kingfisher Construction

Architect

Bowman Riley


The brief

Kingfisher Construction appointed Eastledge to deliver the internal partitions, dry lining, taping and jointing, suspended ceilings and fire curtains for a Co-op Funeralcare premises on Morden Road, Mitcham, south London. Bowman Riley was the architect. The fit-out was registered under BREEAM Refurbishment and Fit Out 2014, targeting Very Good.

The building brings together clinical and hygiene-critical rooms, ground-floor public and admin spaces, and first-floor staff areas. That called for fire-rated and acoustic partitions where the specification required them, a cleanable ceiling finish in the hygiene areas, and a consistent commercial finish through the corridors and public rooms.

Finished suspended ceiling and two-tone partition walls along a corridor at Co-op Funeralcare, Morden Road, Mitcham

Scope

Our team supplied and installed metal stud partitions and linings, including 30 to 120 minute fire-rated walls, acoustic partitions, linings and ply pattressing; taping and jointing to a Level 3 finish; a first-floor plasterboard bulkhead; suspended ceilings; and fire curtains. The walls, plasterboard, taping and jointing, and suspended ceilings ran through the clinical rooms, the ground-floor public and admin spaces, the corridors and the first-floor staff areas.

Hygienic wall cladding on the project was carried out by others and was not part of the Eastledge package.

Products

The partition and dry lining package used Siniat GTEC Standard Board, Siniat GTEC dB Board and Siniat Fire Core Board, with Knauf Soundshield Plus 15 mm in the acoustic wall type. Metalwork was Hadley and Metsec Speedline, with Superglass APR insulation.

Suspended ceilings were installed as Rockfon Artic A24 and Rockfon CleanSpace Essential A24, both 600 x 600 square edge, on a Rockfon T24 grid. Anti-corrosive T24 grid was used where the specification required it.

Fire curtains were Firefly Apollo Lite.

The challenge

The main challenge was design changes throughout the build, in particular the deflection design. The portal frame had more movement than a standard partition head could take, so a non-standard deflection head detail had to be developed with Kingfisher Construction, Bowman Riley and the structural engineer while our team was already on site. Manufacturer head details were needed for the walls affected by that movement, including walls under the mezzanine.

Our team reduced labour on site while the detail was being resolved, then built to the agreed head detail once it was confirmed, boarding to the deflection level and sealing the heads so the detail was not compromised. The deflection design also meant some partition types were changed from Hadley to Speedline metal. Bowman Riley issued revised drawings for the affected wall types, and our team agreed the revised types with the design team, including the acoustic performance required for BREEAM.

Separately, the specified ceiling tiles were not available. Our team installed Rockfon Artic A24 and Rockfon CleanSpace Essential A24 as the agreed alternatives, on Rockfon T24 grid. The change was confirmed as compatible with the targeted BREEAM credits, and Bowman Riley issued an updated ceiling plan.

Delivery

Work started on site in August 2026 and completed in November 2026. The package was sequenced with the main contractor's programme, including the mechanical and electrical first fix above the ceilings.

Outcome

The Co-op Funeralcare premises on Morden Road, Mitcham, was completed with Eastledge's partitions, dry lining, taping and jointing, suspended ceilings and fire curtains in place. Kingfisher Construction was the main contractor and Bowman Riley was the architect. The package ran from August to November 2026.

Further context is on Dry Lining, Partitions, Fire-Rated Partitions, Suspended Ceilings and London. This funeral care fit-out is separate from the Co-op retail refurbishment programme.

Get in touch

Planning a similar project?

We work with estates teams, main contractors and designers across education, healthcare and commercial. Tell us about your brief and we'll come back quickly with a clear next step.

Where this sits

Services, areas and contractor packages

Related projects

More work like this

All projects →

Get in touch

Looking for similar work in retail?

Tell us about the building, the programme and your priorities. We'll come back with a clear next step within one working day.

Request a quote

Pre-filled for Dry Lining for Retail in London.

We'll only use your details to respond to your enquiry.